Installation of anti-terrorism bollards at Chester Racecourse

Background

The Council is working with Chester Racecourse to enable them to install sockets for anti-terrorism bollards on roads around the venue. There is no intelligence to suggest that there is a specific threat posed to the Racecourse. However, the vehicle security bollards will prevent a hostile vehicle or accidental vehicle from entering the crowded pedestrian areas. The work is scheduled to begin in April and will require several road closures while it takes place.

Not only will the bollards protect racecourse visitors on race days, but they will mean road closures on race days can be implemented and removed much more quickly. So there will be less disruption in the City during race meetings. There will be some disruption with a number of road closures but the end result will mean smoother traffic in the city during race events.

Latest update

The current schedule of road closures for this work is as follows:

The current schedule of road closures for this work is as follows:

  • Black Friars Start 2 April 2024 - Ends 5 April 2024 - Completed
  • Grey Friars Start 2 April 2024 - Ends 5 April 2024 - Completed
  • City Walls Road Start 8 April 2024 - Ends 12 April 2024 - Completed
  • Nuns Road Start 9 April 2024 - Ends 20 April 2024 - Completed
  • St Nicholas St Mews Start 11 April 2024 - Ends 20 April 2024 - Completed
  • Stanley Street Start 12 April 2024 - Ends 26 April 2024
  • New Crane Street Start 24 April 2024 - Ends 3 May 2024
  • Watergate Street Start 24 April 2024 - Ends 3 May 2024