Micro asphalt programme

Our micro asphalt surface treatment programme is due to start soon. This treatment programme is a road maintenance process which involves laying a thin layer over the top of the existing road to seal the surface and restore grip, thereby extending the active lifespan of the road.

Micro asphalt cures quickly and can usually be driven on less than an hour after application. Its ability to reshape and re-profile existing surfaces ensures minor defects, such as small potholes and cracks, are sealed to stop water getting in to cause further damage.

On average, micro asphalt extends the ‘life expectancy’ of a road by five to seven years. It as has a much-reduced environmental impact compared to standard resurfacing techniques as it is a non-polluting, cold-applied, zero-emissions material.

The programme will begin in January 2020 with any necessary preparation works being carried out ahead of the full micro asphalt treatment, which will take place between March and April 2020. Preparation works will include any patching needed, cutting back overhanging trees, plus clearing debris and dirt at the edges of the carriageway.

Our micro-asphalt treatment programme is detailed below, however dates may vary slightly dependent on weather conditions. We will update this information as soon as we can if our programme is affected.

Please note: During these dates the road will be closed with no through route, access will only be for residents.

Work dates 2020

 

Welsh Road

  • Preparation works: Complete
  • Proposed work dates: Complete
 

Ledsham Hall Lane

  • Preparation works: Complete
  • Proposed work dates: Complete
 

Winstanley Road

  • Preparation works: none required
  • Proposed work dates: Complete

Sunningdale Way

  • Preparation works: Complete
  • Proposed work dates: Complete

Greenfields Drive

  • Preparation works: Complete
  • Proposed work dates: Complete
 

Waterworks Lane

  • Preparation works: Complete
  • Proposed work dates: Complete

Oakfield Road

  • Preparation works: Complete
  • Proposed work dates: Complete
 

Horston Road

  • Preparation works: none required
  • Proposed work dates: Complete

Horston Garden

  • Preparation works: none required
  • Proposed work dates: Complete

Horston Crescent

  • Preparation works: none required
  • Proposed work dates: Complete

Saltersgate

  • Preparation works: none required
  • Proposed work dates: Complete

Humber Road

  • Preparation works: none required
  • Proposed work dates: Monday 16 March - Tuesday 17 March

Chilton Drive

  • Preparation works: none required
  • Proposed work dates: Friday 13 March

Antrim Drive

  • Preparation works: none required
  • Proposed work dates: Friday 13 March

Cartmel Drive

  • Preparation works: none required
  • Proposed work dates: Monday 16 March

Merton Road

  • Preparation works: Complete
  • Proposed work dates: Wednesday 18 March - Thursday 19 March

Budworth Road

  • Preparation works: Complete
  • Proposed work dates: Wednesday 18 March

Falcon Road

  • Preparation works: none required
  • Proposed work dates: Tuesday 17 March

Nantwich Road

  • Preparation works: Complete
  • Proposed work dates: Tuesday 17 March - Wednesday 18 March

Talbot Road

  • Preparation works: Complete
  • Proposed work dates: Thursday 19 March
 

Stanney Lane Service Road 1 and 2

  • Preparation works: Complete
  • Proposed work dates: Friday 20 March - Saturday 21 March

Stanney Lane Service Road 3

  • Preparation works: Complete
  • Proposed work dates: Sunday 22 March

Stanney Lane Service Road 4

  • Preparation works: Complete
  • Proposed work dates: Sunday 22 March

Sandringham Gardens

  • Preparation works: none required
  • Proposed work dates: Friday 20 March

Denbigh Gardens

  • Preparation works: none required
  • Proposed work dates: Friday 20 March
 

Northgate Avenue (including Eardswick Close)

  • Preparation works: Complete
  • Proposed work dates: Monday 23 March - Tuesday 24 March

Heron Place

  • Preparation works: none required
  • Proposed work dates: Tuesday 24 March

Wroxham Close

  • Preparation works: none required
  • Proposed work dates: Tuesday 24 March

Hatherton Way

  • Preparation works: Complete
  • Proposed work dates: Monday 23 March - Tuesday 24 March

Foxwist Close

  • Preparation works: none required
  • Proposed work dates: Monday 23 March

Gonsley Close

  • Preparation works: none required
  • Proposed work dates: Monday 23 March

Hankelow Close

  • Preparation works: none required
  • Proposed work dates: Monday 23 March

Baristow Close

  • Preparation works: none required
  • Proposed work dates: Monday 23 March
 

Stannage Lane

  • Preparation works: Complete
  • Proposed work dates: Wednesday 25 March - Thursday 26 March
 

Dog Lane

  • Preparation works: Complete
  • Proposed work dates: Friday 27 March
 

Burton Lane

  • Preparation works: Complete
  • Proposed work dates: Friday 27 March - Monday 30 March
 

Oaklands Avenue

  • Preparation works: Complete
  • Proposed work dates: Wednesday 1 April - Thursday 2 April

Oaklands Crescent

  • Preparation works: Complete
  • Proposed work dates: Tuesday 31 March - Wednesday 1 April

Rookery Drive

  • Preparation works: Complete
  • Proposed work dates: Thursday 2 April

Greenlands (including two cul-de-sacs)

  • Preparation works: Complete
  • Proposed work dates: Monday 30 March – Tuesday 31 March
 

Regency Court

  • Preparation works: Complete
  • Proposed work dates: Thursday 2 April – Friday 3 April

School Lane

  • Preparation works: Complete
  • Proposed work dates: Friday 3 April – Saturday 4 April
 

Manor Road

  • Preparation works: none required
  • Proposed work dates: Saturday 4 April - Sunday 5 April

Clifton Crescent

  • Preparation works: Complete
  • Proposed work dates: Sunday 5 April

Access off Ashton Drive (rear of shops)

  • Preparation works: none required
  • Proposed work dates: Monday 6 April

117-139 Ashton Drive

  • Preparation works: Complete
  • Proposed work dates: Monday 6 April

Riversdale

  • Preparation works: Complete
  • Proposed work dates: Monday 6 April - Tuesday 7 April

Ashton Drive

  • Preparation works: Complete
  • Proposed work dates: Monday 6 April

Belvedere Close

  • Preparation works: none required
  • Proposed work dates: Wednesday 8 April - Thursday 9 April

Hayes Crescent

  • Preparation works: Complete
  • Proposed work dates: Thursday 9 April - Tuesday 14 April

St Hilda's Drive

  • Preparation works: Complete
  • Proposed work dates: Tuesday 14 April - Wednesday 15 April

Howey Lane

  • Preparation works: none required
  • Proposed work dates: Wednesday 15 April - Friday 17 April

 

Share this page

Terms and conditions Privacy policy Cookies Contact                      

We use cookies

Cheshire West and Chester Council use cookies to ensure that we give you the best experience on our website. If you continue without changing your settings, we'll assume that you are happy to receive all cookies on our website. However, if you would like to, you can change your cookie settings at any time.